Port Sudan Strategic Terminal Project

Investor: Ministry of Energy and Mining / Sudanese Petroleum Corporation

Scope of works: Metering SKIDs - Basic and Detail Design ( Gasoline, Diesel, Jet A1, LPG )

  • Pipeline from new depot to loading gantry - 6" ( SKID A )
  • Pipeline from new depot to old depot refinery - 12" ( SKID B )
  • Pipeline from new depot to & from Dama Dama + export - 14" ( SKID C )
  • Pipeline from new depot to Dama Dama for export - 16" ( SKID D )
  • Pipeline from old depot to new depot - 16" ( SKID E )
  • Pipeline to loading gantry - 6" ( SKID F )

Date of realizations: 2014


Port Terminal Burgas East 2

Investor: BMF PORT BURGAS EAD

Scope of works: LPG Metering SKID Basic and Detail Design

  • Metering run of Ship Tanker unloading DN200/DN100/PN40 ( SKID A )
  • Metering run of Truck Tanker loading DN80/DN50/PN40 ( SKID B )
  • Metering run of Railcar Tanker loading DN80/DN50/PN40 ( SKID C )

Date of realizations: 2014


Extending SMO Trebišov

Investor: Progress Trading SpA

Scope of work:

  • Project management for planning
  • A project for building permit
  • A project for building work

Investment activities:

Date: 2010


Fuel storage, Wangzhuang - China

Investor: PetroChina Company Limited

Scope of work:

  • Documentation for land management
  • Documentation for building permit

Investment activities:

Date: 2010